Saudi Government Tenders and Procurement Law 1448 AH: Contracting Methods, Guarantees, and Grievances

The official gazette Umm Al-Qura published in its issue 5180, dated Friday 22 Rabi' Al-Awwal 1448 AH (corresponding to 4 September 2026), the details of the new Government Tenders and Procurement Law, approved by Royal Decree No. (M/76) dated 27/02/1448 AH. The new law replaces the previous one issued in 1440 AH and enters into force 120 days after its publication, i.e., starting from 3 January 2027 source.
What is the new Government Tenders and Procurement Law?
A legislative framework of 101 articles distributed across seven chapters, regulating the procedures for ministries, authorities, and government agencies to purchase works, goods, and services. It was issued by Royal Decree No. (M/76) dated 27/02/1448 AH and published in Umm Al-Qura on 22 Rabi' Al-Awwal 1448 AH (4 September 2026) source.
What are the law's five objectives?
Article Two stipulates five goals: regulating procedures and preventing abuse of influence to protect public funds; achieving best value for public money at fair competitive prices; enhancing integrity, competition, and equality; ensuring transparency in all procedures; and promoting economic development source.
When does the new law take effect?
120 days after its publication in the official gazette, i.e., from 3 January 2027. Until that date, the previous law (1440 AH) remains in force source.
What contracting methods does the law approve?
Article twenty-eight states that the default method is open competition, with the following exceptions source:
| Method | When Used (Summary from Text) |
|---|---|
| Open Competition | The default for all contracts, subject to publicity, transparency, and equal opportunity |
| Limited Competition | When works are available from a limited number of suppliers, or the estimated value does not exceed five hundred thousand riyals with at least five competitors invited, and urgent cases |
| Two-Stage Competition | When final specifications and conditions cannot be precisely defined due to the complex nature of the works |
| Direct Purchase | Arms and military equipment via the General Authority for Military Industries; sole-source provider with no acceptable alternative; or cost not exceeding one million riyals |
| Framework Agreement | When quantities, scope of works, or execution dates cannot be determined in advance |
| Reverse Electronic Auction | Successively reduced bids within a set period to select the lowest price, provided detailed specifications and a competitive market exist |
What is the direct purchase ceiling in the new law?
One million riyals, the maximum threshold for direct purchase per the article on contracting methods, compared to lower limits in the previous law source.
What are the bid and performance guarantees in the new law?
- Bid Guarantee: Starts at 1% of the bid value (Article 41); bids submitted without it are rejected.
- Exemption from Bid Guarantee: Applies to direct purchase, competitions, inter-governmental contracts, contracts with non-profit entities, and local small and medium enterprises.
- Performance Guarantee: 5% of the contract value, submitted within 15 business days of award notification, extendable for a similar period (Article 61).
- Cases Where Performance Guarantee Is Not Required: When the value of works does not exceed one hundred thousand riyals, and inter-governmental contracts.
Guarantee details are derived from the law and the Implementing Regulations available on the Ministry of Finance website source.
How are tenders announced and where can suppliers track them?
- Open competitions are announced on the Unified Electronic Portal (Etimad Platform), supervised by the Ministry of Finance source.
- Entities are required to publish their annual procurement plans on the portal (Article 12).
- Supplier journey: Register on Etimad → Track tenders and plans → Purchase tender documents and submit bid with bid guarantee → Await evaluation and assessment → Award announcement → Submit performance guarantee and sign contract.
What is the grievance period and procedure?
The standstill period (grievance review window) does not exceed 10 business days, starting from the date unsuccessful competitors are notified of the winning bid. The right to grievance is guaranteed for competitors, and the government entity reviews it during this period source.
Key Figures in the New Law
- Number of Articles: 101
- Number of Chapters: 7
- Number of Definitions: 21 terms
- Direct Purchase Ceiling: One million riyals
- Bid Guarantee: From 1%
- Performance Guarantee: 5% of contract value
- Performance Guarantee Submission Deadline: 15 business days (extendable)
- Grievance Period: Not exceeding 10 business days
- Effective Date: 3 January 2027 (120 days after publication)
Summary and What to Watch
The new law raises the direct purchase ceiling to one million riyals, lowers the bid guarantee to 1%, and compresses the grievance period to 10 business days — all indicators of accelerated procedures and reduced barriers for suppliers. You should review the full text of the law and the Implementing Regulations on the Ministry of Finance website before any actual contracting, and monitor Etimad Platform updates for the activation of new procedures starting January 2027.