Red Sea Global launches 340MW solar-powered utilities system off-grid

ف
فريق تحرير صقر الجزيرةفريق التحرير
||805 views
مقارنة شاملة بين نيوم والقدية ومشروع البحر الأحمر: أهداف وتمويل وتأثيرات

Red Sea International has started commercial operation of an integrated renewable-energy utilities system that runs independently of the national grid, according to a statement from Red Sea International and ACWA Power. The system includes a 340 MW AC solar plant and supplies the hotels operating in the destination and Red Sea International Airport. According to Al Eqtisadiah, this is the first operation of its kind in the destination since the commercial operation certificate was signed.

Red Sea International operates the Red Sea destination. The project company, Red Sea Utilities for Energy, was established by ACWA Power together with SPIC Huanghe Hydropower, Tabreed Saudi Arabia, and Red Sea Utilities, a subsidiary of Red Sea International. Under the agreement, a 25-year concession period begins.

What has started operating?

The system runs five main services from a single platform, according to the announcement. These services are:

  • Renewable power generation.
  • Drinking water production.
  • Wastewater treatment.
  • District cooling.
  • Waste management.

The solar plant works alongside a battery storage system with a capacity of 1,227 MWh. According to the announcement, it is the largest off-grid battery system in the world. The storage system allows the destination to keep receiving power during night hours.

How much energy will the system produce?

The generation system can produce up to 760 thousand MWh of clean energy a year. This is expected to avoid emissions of about 600 thousand tonnes of carbon dioxide annually. The system is designed to meet the initial energy demand, with room to expand as the destination's future phases come online.

What are the key figures?

  • Solar plant capacity: 340 MW AC (Al Eqtisadiah)
  • Battery storage capacity: 1,227 MWh (Al Eqtisadiah)
  • Expected annual output: up to 760 thousand MWh (Al Eqtisadiah)
  • Carbon dioxide emissions avoided: about 600 thousand tonnes a year (Al Eqtisadiah)
  • Concession period: 25 years (Al Eqtisadiah)

What does the Trojena contract mean for the Red Sea destination?

Red Sea Global, listed on the main market of the Saudi exchange (Tadawul), signed a contract with WeBuild S.p.A. for integrated facilities management services, including operation and maintenance, for the Trojena project in NEOM. The contract value exceeds SAR 202.8 million, excluding VAT, and its term is two years. According to Al Eqtisadiah, the services cover housing, catering, security, facilities maintenance, waste management, and fire safety for the main workers' camp and a secondary camp supporting the Trojena dam.

In its disclosure on Tadawul, the company said the financial impact of the contract will begin to appear from the first quarter of 2026. The newspaper notes that the disclosure was published in December 2025. This figure should therefore be read as a declared contractual commitment, not as an audited financial result.

What do the sources not cover?

The sources available for this update do not address the current status of NEOM or Qiddiya, so this version does not compare the three projects. The sources also do not include an updated total cost for any Red Sea project, the number of resorts currently open, or opening dates for the destinations beyond the announcements cited above.

The operational details of the energy system and the Trojena contract are available, and this article relies on them.

What should readers follow next?

If you follow the Red Sea destination, first watch for official updates on the solar system's performance and storage capacity in the coming period. Also follow Red Sea Global's disclosures on the Tadawul website, since that is where the financial impact of contracts is published. If you need a comparison with NEOM or Qiddiya, use recent sources that state each project's status with a date.